Project Update: Gulf Star Marina (1/29/20)

Things are coming to a head at Gulf Star Marina, it’s been an exciting project as we draw nearer to the finish line. As LTW continues programming on the automated system, we are putting the shuttles and boat lift through the test. That’s 11 tons of concrete blocks! We’re making the utility connections under [...]

By |2020-02-07T11:37:15+00:00January 29th, 2020|Gulf Star Marina|0 Comments

Project Update: Gulf Star Marina (1/7/20)

Happy New Year to all! As we usher in 2020 at Gulf Star Marina, we’ve reached a point where all of our structural elements are in place, and the final architectural finishes are underway. The ASAR crane has been assembled, and programming of the automated system will begin this week. The boat lift and [...]

By |2020-01-07T18:33:27+00:00January 7th, 2020|Gulf Star Marina, News|0 Comments

Project Update: Gulf Star Marina (11/25/19)

Work is progressing swiftly at Gulf Star Marina! We're currently working on putting in the boat shuttle guide rails with the help of Kelly Brothers Inc. We're also doing miscellaneous grade work around the jobsite, and preparing to start working on metal framing for the roof.

By |2019-11-25T16:39:38+00:00November 25th, 2019|Gulf Star Marina, News|0 Comments

METSTRADE 2019 is a Wrap!

ASAR and Safe Harbour Dry Stacks have been annual exhibitors at METSTRADE in Amsterdam for the past 3 years. As this year's event came to an end today, our #1 goal remains, and that is to bringing awareness to marine industry professionals on the advantages of concrete construction and automation. We are redefining the future marina! #METSTRADE2019 [...]

By |2019-11-21T18:52:10+00:00November 21st, 2019|News|0 Comments

Project Update: Gulf Star Marina (11-8-19)

At Gulf Star Marina, our ASAR – A Smart Storage Solution Crane’s construction is well underway! The main structure has been lifted in and assembled, so we were finally able to close off the roof. Now we’re working on finishing the crane rails, boat exit, and the new Doc Ford’s Rum Bar & Grille parking lot. [...]

By |2019-11-13T22:03:11+00:00November 8th, 2019|Gulf Star Marina|0 Comments

Project Update: Gulf Star Marina (10-29-19)

Yesterday, our partners at LTW began piecing together the beginnings of the ASAR stacker crane being installed at Gulf Star Marina. Over the next couple of weeks, we’ll be watching as they fly in the crane masts and machinery through the rooftop opening of the first-ever fully-automated SMART marina. Take a look inside at our [...]